
A warning during lifting
Grain discharge was stopped after the hoisting rope on a bulk carrier’s No. 3 crane developed abnormal local slackening. The rope had not completely parted. The instruction was to investigate the condition of the lifting arrangement and the mechanism behind the loss of normal guidance and tension.
The electro-hydraulic crane had a nominal 30-tonne capacity. Its 30 mm galvanised, non-rotating hoisting rope had been installed in September 2020. Inspection on 10 March 2025 concentrated on whether the visible event reflected a new overload, existing deterioration or a combination of operating load and reduced rope capacity.
Different conditions along the same rope
The section passing through the sheaves appeared satisfactory on visual inspection, with measured diameters between 30.0 and 30.6 mm. The section wound on the drum presented a markedly different condition.
Over approximately 1.70 m, the drum section showed cuts 2–3 mm deep, local crushing, displaced strands and unravelled wires. A local diameter of 33 mm was recorded. These observations demonstrated why an assessment limited to the easily visible running section would not describe the condition of the complete rope.
The distribution and character of the damage were interpreted as evidence of deterioration developing before the reported slackening. Grease and accumulated dirt were considered potential obstacles to effective visual examination. The available inspection record did not establish the precise date at which each defect had formed.
The load assessment and its assumptions
The rope certificate recorded a minimum breaking load of 763 kN. The assessment compared this with an estimated grab-and-cargo mass, using an 11 m³ grab capacity, an estimated empty grab mass and the wheat stowage factor.
Because technical documentation for the grab was unavailable, the empty weight and resulting total load were estimates. A rope breaking-load figure must also be related to the actual reeving, rope parts, crane load chart and applicable safety factors before it can be used to establish the permitted suspended load.
Loading therefore remained a relevant line of investigation; a precise percentage overload was not established. The severe physical deterioration was directly observed; the exact degree of any operational exceedance required additional equipment documentation.
Inspection history and corrective action
The documentary review reported that a crane certificate had expired. That was relevant to the inspection history, but neither an expired nor a current certificate can replace examination of the rope’s actual condition at the time of use.
The proposed mechanism involved a damaged drum section with reduced ability to carry and maintain load uniformly, followed by instability and abnormal slackening during grab operation. It remained a reconstruction based on the observed condition and reported sequence.
The rope was replaced on the day of the survey. The case record describes electrical checks and functional testing before the crane returned to operation the following afternoon. The important finding was that substantial local deterioration had existed in a section not represented by the apparently sound rope passing through the sheaves.
